Heap leaching area, the construction activities of which were started in September 2015, was completed in accordance with the project. The construction of the heap leaching covers the excavation, filling, underliner laying and compaction, geotextile-geomembrane surface coating and overliner laying activities of the 175.000 m² area with 10 cells in total. Within the scope of these activities, the construction of the last two cells was started at the end of May 2018 and all compaction and impermeability tests were successfully completed as of the end of October, and the cells were made ready to operate.
Nowember 6, 2018